Exam
Code: P2020-795
Exam Name: IBM Decision Optimization Technical Mastery Test v2
One year free update, No help, Full refund!
P2020-795 torrrent Total Q&A: 45 Questions and Answers
Last Update: 12-11,2016
Exam Name: IBM Decision Optimization Technical Mastery Test v2
One year free update, No help, Full refund!
P2020-795 torrrent Total Q&A: 45 Questions and Answers
Last Update: 12-11,2016
P2020-795 study dumps Detail: P2020-795 torrrent
NO.1 A technical seller can identify an IBM Decision Optimization Center (DOC)
opportunity versus an IBM CPLEX opportunity when the customer's:
A. Business users want the ability to run what-if analysis and scenario comparisons.
B. OR team wishes to link the engine to IBM SPSS Modeler.
C. IT team is interested in embedding the engine into a proprietary application.
D. OR team has an existing OPL model and would like to solve it on a single desktop
Answer: A
P2020-795 sample
NO.2 A customer wants to deploy an optimization based solution in a scalable and high availability (HA) deployment environment that provides failover and load balancing capabilities. Which
application server can be used for deploying Decision Optimization Center server components to provide an HA environment?
A. WebSphere Application Server Community Edition
B. WebSphere Application Server
C. Oracle WebLogic Server
D. WebSphere Application Server Network Deployment
Answer: B
P2020-795 cheap P2020-795 best
NO.3 A technical seller conducts a discovery workshop with a client. What is important to know when assessing the business use cases of the client?
A. Compare the current to the desired situation and determine relevant key performance indicators.
B. Evaluate the complexity of the optimization model and estimate key performance indicators.
C. Get a deep understanding of the desired situation and the client's total revenue.
D. Evaluate the complexity of the optimization model and determine the client s total revenue
Answer: A
P2020-795 materials
NO.4 A manufacturing client has asked for a Proof of Concept on production scheduling. What is the first thing the technical seller will need to work on?
A. Start working on a first version of the mathematical model to better assess the complexity.
B. Determine the components that need to be licensed and their sizing.
C. Find out when all required data will be available.
D. Ensure that there is a clear agreement on objectives, expected outcomes and the responsibilities of each party.
Answer: D
A. Business users want the ability to run what-if analysis and scenario comparisons.
B. OR team wishes to link the engine to IBM SPSS Modeler.
C. IT team is interested in embedding the engine into a proprietary application.
D. OR team has an existing OPL model and would like to solve it on a single desktop
Answer: A
P2020-795 sample
NO.2 A customer wants to deploy an optimization based solution in a scalable and high availability (HA) deployment environment that provides failover and load balancing capabilities. Which
application server can be used for deploying Decision Optimization Center server components to provide an HA environment?
A. WebSphere Application Server Community Edition
B. WebSphere Application Server
C. Oracle WebLogic Server
D. WebSphere Application Server Network Deployment
Answer: B
P2020-795 cheap P2020-795 best
NO.3 A technical seller conducts a discovery workshop with a client. What is important to know when assessing the business use cases of the client?
A. Compare the current to the desired situation and determine relevant key performance indicators.
B. Evaluate the complexity of the optimization model and estimate key performance indicators.
C. Get a deep understanding of the desired situation and the client's total revenue.
D. Evaluate the complexity of the optimization model and determine the client s total revenue
Answer: A
P2020-795 materials
NO.4 A manufacturing client has asked for a Proof of Concept on production scheduling. What is the first thing the technical seller will need to work on?
A. Start working on a first version of the mathematical model to better assess the complexity.
B. Determine the components that need to be licensed and their sizing.
C. Find out when all required data will be available.
D. Ensure that there is a clear agreement on objectives, expected outcomes and the responsibilities of each party.
Answer: D